Build Timeline

DATE
MILESTONE
06.08.2012
Our House. Our Home.
06.08.2012
HANDOVER.  382 days  since Site Start.
06.08.2012
Final PRACTICAL COMPLETION INSPECTION (PCI)
01.08.2012
Another Final QA Inspection by M?
30.07.2012
Problem with telephone lead-in to Telstra pit
(No phone, No cable internet)
30.07.2012
Bigpond to connect new house to Cable Internet
27.07.2012
Telstra to move telephone service from old house to new
20.07.2012
ONE YEAR FROM SITE START (Day 365)
05.07.2012
Another Final QA Inspection by M?
02.07.2012
Pre-Handover Independent Inspection (3rd of 3) by NHI
29.06.2012
PRACTICAL COMPLETION INSPECTION (PCI)
28.06.2012
Final QA Inspection by M.
17.06.2012
More QA.  “Red Dot Special”
21.05.2012
QA (by the CM) failed.  Cornices need replacing.
16.05.2012
THREE HUNDRED DAYS FROM SITE START (Day 300)
11.05.2012
Timber Venetians (front only) installed.
10.05.2012
Lots done today!!!
Gas Hot Water System; Appliances connected; Kitchen Island Bench stone-top re-installed; 
09.05.2012
Carpet’s laid
08.05.2012
Carpet laying commences
07.05.2012
Repaint, Restain, Retouch, Fix
04.05.2012
Timber Flooring Completed
03.05.2012
Timber Floor laying commences
27.04.2012
Fit Offs Completed
23.04.2012
Fit Offs Commenced
21.04.2012
House/Site Cleaning
15.04.2012
Driveway completed (and side pathway concreted)
01.04.2012
Toilets, baths, basins, bathroom fittings completed
30.03.2012
Plumbing fit-off commences
28.03.2012
Electrical fit-off commences
28.03.2012
Bathroom shower glass frames installed
28.03.2012
Floor Tiling complete
27.03.2012
Kitchen glass splashback installed
27.03.2012
Alarm system installed
26.03.2012
Wardrobe fittings installed
26.03.2012
Wall Tiling complete
22.03.2011
Fixing Stage Payment
20.03.2012
Garage Doors (Panel Glide and Roller Door) installed
17.03.2012
Balcony railings installed
17.03.2012
Caesarstone benchtops installed
17.03.2012
Outdoor Room Timber Deck build completed
12.03.2012
Outdoor Room Timber Deck build commences
11.03.2012
Heating vents installed
08.03.2012
FIXING STAGE COMPLETE
06.03.2012
Wall/Floor Tiling Commences
05.03.2012
Painting Complete
24.02.2012
Painting Commences
13.02.2012
Plaster Complete
09.02.2012
Stairs built and Cabinets installed
08.02.2012
Cabinets delivered
06.02.2012
TWO HUNDRED DAYS FROM SITE START (Day 200)
03.02.2012
More plastering
20.01.2012
Plastering commenced
16.01.2012
Build work recommences? (Fixing Stage)
24.12.2011
CHRISTMAS SHUTDOWN (No Work)
19.12.2011
Lock- Up Stage Payment
14.12.2011
Pre- Plaster Quality Check (M's) Complete
12.12.2011
LOCK- UP STAGE COMPLETE
05.11.2011
External Cladding Complete
29.10.2011
ONE HUNDRED DAYS FROM SITE START (Day 100)
25.10.2011
Pre- Plaster Stage Independent Inspection (2nd of 3) by NHI
22.10.2011
Brickwork Complete
07.10.2011
Frame Stage Payment
28.09.2011
FRAME STAGE COMPLETE
26.09.2011
Underground Power Pit install commences
22.09.2011
Brickwork commences
21.09.2011
Frame Stage Independent Inspection (1st of 3) by NHI
19.09.2011
Roof Complete (first floor only)
16.09.2011
Fascia/Gutter Complete
01.09.2011
Wall Frame Complete
20.08.2011
Frame's coming up
16.08.2011
Base Stage Payment
11.08.2011
BASE STAGE COMPLETE
10.08.2011
We got a slab!!!
30.07.2011
Foundations Blessed (by Fr. Pat)
21.07.2011
SITE START (Day 0)
13.07.2011
Ordering Complete
01.07.2011
Approval to Commence Construction
14.06.2011
2nd Soil Test, 2nd Survey & Boundary Survey Received
06.06.2011
DEMOLITION COMPLETED
30.05.2011
Site all set for demolition
05.05.2011
Abolishments (Gas & Electricity) Completed
18.04.2011
Asset Protection Permit Issued
13.04.2011
Finance Approval
13.04.2011
Planning Permit Issued
04.04.2011
Tile Selections @ Beaumont Tiles
21.03.2011
Building Permit Approved
08.03.2011
Balance of Deposit Paid
28.02.2011
CONTRACT SIGNED
01.02.2011
Electrical Consultation @ Lifestyle National
27.01.2011
More Specification variations done
20.01.2011
Colour Selection @ Studio M
14.01.2011
PC ESTIMATE COMPLETED
07.12.2010
Sale Acceptance, $1K downpayment
01.12.2010
The Liberty 42 journey begins ...
27.11.2010
Decides on M's Liberty 38/42, instead
30.10.2010
Our very first appointment with M
15.10.2010
Decides on M's Whittaker 45
01.10.2010
Started looking at display homes ... M or PD?
01.09.2010
We had a dream