DATE
|
MILESTONE
|
06.08.2012
|
Our
House. Our Home.
|
06.08.2012
|
HANDOVER. 382
days since Site Start.
|
06.08.2012
|
Final
PRACTICAL COMPLETION INSPECTION (PCI)
|
01.08.2012
|
Another
Final QA Inspection by M?
|
30.07.2012
|
Problem
with telephone lead-in to Telstra pit
(No
phone, No cable internet)
|
30.07.2012
|
Bigpond
to connect new house to Cable Internet
|
27.07.2012
|
Telstra
to move telephone service from old house to new
|
20.07.2012
|
ONE YEAR FROM SITE START (Day 365)
|
05.07.2012
|
Another
Final QA Inspection by M?
|
02.07.2012
|
Pre-Handover
Independent Inspection (3rd of 3) by NHI
|
29.06.2012
|
PRACTICAL
COMPLETION INSPECTION (PCI)
|
28.06.2012
|
Final
QA Inspection by M.
|
17.06.2012
|
More
QA. “Red Dot Special”
|
21.05.2012
|
QA
(by the CM) failed. Cornices need
replacing.
|
16.05.2012
|
THREE
HUNDRED DAYS FROM SITE START (Day 300)
|
11.05.2012
|
Timber
Venetians (front only) installed.
|
10.05.2012
|
Lots
done today!!!
Gas
Hot Water System; Appliances connected; Kitchen Island Bench stone-top
re-installed;
|
09.05.2012
|
Carpet’s
laid
|
08.05.2012
|
Carpet
laying commences
|
07.05.2012
|
Repaint,
Restain, Retouch, Fix
|
04.05.2012
|
Timber
Flooring Completed
|
03.05.2012
|
Timber
Floor laying commences
|
27.04.2012
|
Fit
Offs Completed
|
23.04.2012
|
Fit
Offs Commenced
|
21.04.2012
|
House/Site
Cleaning
|
15.04.2012
|
Driveway
completed (and side pathway concreted)
|
01.04.2012
|
Toilets,
baths, basins, bathroom fittings completed
|
30.03.2012
|
Plumbing
fit-off commences
|
28.03.2012
|
Electrical
fit-off commences
|
28.03.2012
|
Bathroom
shower glass frames installed
|
28.03.2012
|
Floor
Tiling complete
|
27.03.2012
|
Kitchen
glass splashback installed
|
27.03.2012
|
Alarm
system installed
|
26.03.2012
|
Wardrobe
fittings installed
|
26.03.2012
|
Wall
Tiling complete
|
22.03.2011
|
Fixing
Stage Payment
|
20.03.2012
|
Garage
Doors (Panel Glide and Roller Door) installed
|
17.03.2012
|
Balcony
railings installed
|
17.03.2012
|
Caesarstone
benchtops installed
|
17.03.2012
|
Outdoor
Room Timber Deck build completed
|
12.03.2012
|
Outdoor
Room Timber Deck build commences
|
11.03.2012
|
Heating
vents installed
|
08.03.2012
|
FIXING STAGE
COMPLETE
|
06.03.2012
|
Wall/Floor
Tiling Commences
|
05.03.2012
|
Painting
Complete
|
24.02.2012
|
Painting
Commences
|
13.02.2012
|
Plaster
Complete
|
09.02.2012
|
Stairs
built and Cabinets installed
|
08.02.2012
|
Cabinets
delivered
|
06.02.2012
|
TWO HUNDRED DAYS FROM SITE START (Day 200)
|
03.02.2012
|
More
plastering
|
20.01.2012
|
Plastering
commenced
|
16.01.2012
|
Build
work recommences? (Fixing Stage)
|
24.12.2011
|
CHRISTMAS
SHUTDOWN (No Work)
|
19.12.2011
|
Lock-
Up Stage Payment
|
14.12.2011
|
Pre-
Plaster Quality Check (M's) Complete
|
12.12.2011
|
LOCK- UP STAGE
COMPLETE
|
05.11.2011
|
External
Cladding Complete
|
29.10.2011
|
ONE
HUNDRED DAYS FROM SITE START (Day 100)
|
25.10.2011
|
Pre-
Plaster Stage Independent Inspection (2nd of 3) by NHI
|
22.10.2011
|
Brickwork
Complete
|
07.10.2011
|
Frame
Stage Payment
|
28.09.2011
|
FRAME STAGE
COMPLETE
|
26.09.2011
|
Underground
Power Pit install commences
|
22.09.2011
|
Brickwork
commences
|
21.09.2011
|
Frame
Stage Independent Inspection (1st of 3) by NHI
|
19.09.2011
|
Roof
Complete (first floor only)
|
16.09.2011
|
Fascia/Gutter
Complete
|
01.09.2011
|
Wall
Frame Complete
|
20.08.2011
|
Frame's
coming up
|
16.08.2011
|
Base
Stage Payment
|
11.08.2011
|
BASE STAGE
COMPLETE
|
10.08.2011
|
We
got a slab!!!
|
30.07.2011
|
Foundations
Blessed (by Fr. Pat)
|
21.07.2011
|
SITE START (Day 0)
|
13.07.2011
|
Ordering
Complete
|
01.07.2011
|
Approval
to Commence Construction
|
14.06.2011
|
2nd
Soil Test, 2nd Survey & Boundary Survey Received
|
06.06.2011
|
DEMOLITION
COMPLETED
|
30.05.2011
|
Site
all set for demolition
|
05.05.2011
|
Abolishments
(Gas & Electricity) Completed
|
18.04.2011
|
Asset
Protection Permit Issued
|
13.04.2011
|
Finance
Approval
|
13.04.2011
|
Planning
Permit Issued
|
04.04.2011
|
Tile
Selections @ Beaumont Tiles
|
21.03.2011
|
Building
Permit Approved
|
08.03.2011
|
Balance
of Deposit Paid
|
28.02.2011
|
CONTRACT SIGNED
|
01.02.2011
|
Electrical
Consultation @ Lifestyle National
|
27.01.2011
|
More
Specification variations done
|
20.01.2011
|
Colour
Selection @ Studio M
|
14.01.2011
|
PC ESTIMATE
COMPLETED
|
07.12.2010
|
Sale
Acceptance, $1K downpayment
|
01.12.2010
|
The
Liberty 42 journey begins ...
|
27.11.2010
|
Decides
on M's Liberty 38/42, instead
|
30.10.2010
|
Our
very first appointment with M
|
15.10.2010
|
Decides
on M's Whittaker 45
|
01.10.2010
|
Started
looking at display homes ... M or PD?
|
01.09.2010
|
We had a dream
|
Build Timeline