Day 0 |
|
Day 100+ |
It's just been over one hundred days, yes, 100+ days (3 1/2 months, or 15 weeks ) since site start and what a sight to behold!!!
We haven't quite reached the completion of the "Lock-Up" Stage, though, yet, but we've been assured we're getting close. Hopefully, in a fortnight, worst case - before Christmas. I'm excited!
So what's expected to be done at the completion of the "Lock-Up" Stage?
According to the
"My Metricon" website ...
"At lock-up stage, your home's bricks, external wall cladding, roof coverings and front and rear doors are installed."
Based on that statement, I'm hoping that the side doors (Laundry and Garage internal access doors) are installed, as well.
So after 100 days, what's been done, so far?
- Slab
- Wall Frame and Roof Trusses
- Windows and Door Frames
- Roof covering (including fascia and guttering), except for the roof coverings on the ground floor (garage, outdoor room and dining room at the rear).
- Insulation (roof and wall insulation), except outdoor room and dining room (no roof covering, yet).
- Brickwork is almost done. Facade, balcony and garage brickwork are still pending.
- Electrical wiring
- Plumbing
- and ... I had two independent building inspections done (Frame and Pre-Plaster).
I went nuts again taking photos. I'm posting a few more photos here.
This is Day 100+ in Jon and Ron's Building a Home journey.
Enjoy!